Bauüberwachung für Erneuerung BÜ km 133,9 und 135,0 Strecke 6207 Bad Liebenwerda
Notice number: 00558864-2026
KEY INFORMATION
- Submission deadline
- • Sep 14, 2026
- Location
- 🇩🇪 Germany
- Contracting authority
- DB InfraGO AG – Geschäftsbereich Fahrweg (Bukr 16)
- Accepted Languages
- German
- Tender type
- Services
- Contract Value
- Published date
- Aug 12, 2026
TENDER DESCRIPTION
This tender seeks comprehensive construction supervision ("Bauüberwachung") for the renewal of level crossings at km 133.9 and 135.0 on route 6207 in Bad Liebenwerda. The scope encompasses performance and quantity determination, amendment/change order processing, defect management, billing, and meticulous digital documentation, including adherence to TSI conformity and services as per the Construction Site Ordinance. Technically, the project requires the use of BIM methodology, specific data formats (e.g., .docx, .pdf, .ifc), the iTWO accounting program, and strict IT security protocols including encryption, regular updates, and unique user IDs. The contract performance is set to begin by December 14, 2026, with on-site execution commencing February 1, 2027, and technical completion scheduled for December 15, 2027, with various key construction milestones throughout. Financial standing requirements mandate declarations regarding tax and social security payments, as well as insolvency or liquidation status.
TENDER BRIEF
The contract timeline includes the following dates and milestones:
Contract Start Date:
- Performance of transferred services is to begin immediately after order placement or on December 14, 2026.
- The start of execution on the construction site is February 1, 2027.
Contract End Date:
- Completion for acceptance (Bau-AN) is August 20, 2027.
- Technical completion is December 15, 2027.
- The activity for technical/construction contract services generally ends with the unconditional acceptance of the final payment by the contractor or the completion of administrative tasks.
- For processing supplementary claims, the latest end of service is the date of legal acceptance of construction services plus 3 months, if delays are not attributable to the contractor.
Key Milestones/Phases:
- Preparatory construction measures: February 24, 2027.
- Start of construction / Decommissioning of level crossing 135 (Berliner Str.): March 10, 2027.
- Signal box - Handover of level crossing 135: June 10, 2027.
- Commissioning of level crossing 135: July 8, 2027.
- Decommissioning of level crossing 133 (Dresdner Str.): July 8, 2027.
- Decommissioning of level crossing 135 (Berliner Str.): July 8, 2027.
- Signal box - Handover of level crossing 135: July 23, 2027.
- Commissioning of level crossing 135: August 20, 2027.
- Technical completion: December 15, 2027.
Sources
- 126FEI88209_0.0_Vertrag BauÜ.pdf — “vergütet werden. Der Bieter/AN versichert, dass Prämien für derartige Versicherungen nicht einkalkuliert sind. §5 Termine und Ausführungsfristen 5.0 5.1 Die Leistungen des AN sind wie folgt zu beginnen und zu vollenden:…”
- 2Rahmenterminplan des AG mit Sperrpausen.xlsx — “3.01_Rahmenterminplan des AG, , Meilensteine,Datum Bauvorbereitende Maßnahmen,2027-02-24 Baubeginn / Außerbetriebnahme BÜ 135 (Berliner Str.),2027-03-10 LST - HdF BÜ 135,2027-06-10 Inbetriebnahme BÜ 135,2027-07-08 Außerb…”
The core scope of work for this tender, identified as "Bauüberwachung" (Construction Supervision), involves several key areas:
1. Performance and Quantity Determination (Leistungs- und Mengenfeststellung): This includes receiving and processing performance data (DA 11 files) from the construction contractor (ANBAU), verifying quantity determination lists, ensuring quality execution, addressing quantity overruns, and requesting corrections to faulty data. It also entails conducting reconciliation meetings for undisputed services and providing monthly status reports with performance evaluations and forecasts.
2. Amendment/Change Order Processing (Nachtragsbearbeitung): The scope covers active management and prevention of change orders, including immediate notification of deviations, timely evaluation of obstruction and additional cost notices, assessing demand and alternative positions, participating in negotiations, and providing detailed factual assessments for change order claims. It also involves participation in the NEuPP (Nachtragseinreich- und Prüfplan) process and assisting in legal disputes.
3. Defect Management (Mängelmanagement): Tasks include recording and preparing defect notifications, tracking and monitoring their rectification, and listing all limitation periods for defect claims related to construction components.
4. Billing (Abrechnung): This involves reviewing billing drawings, quantity determinations, and hourly wage slips. It also requires informing the client of significant quantity changes (over 10%), reviewing all types of invoices (advance, partial, final), and, for electronic billing, continuous reconciliation with the ANBAU regarding rendered services.
5. Documentation (Dokumentation): Core deliverables include creating and maintaining a verifiable construction file (potentially digital), generating digital photographic documentation of key construction phases with detailed descriptions, and ensuring this documentation is available on-site and handed over to the client upon completion. Specific documentation for TSI conformity for relevant measures according to EIGV of DB InfraGO AG is also required.
6. Services under Construction Site Ordinance (Leistungen nach der Baustellenverordnung): This entails performing tasks during the construction execution phase as per § 3, paragraph 3 BaustellV in conjunction with section 3.2 of RAB 30, including updating preliminary announcements for relevant changes.
Sources
- 126FEI88209_1.1_Grundlstg vertragliche facht BÜW bei Verke.pdf — “unstrittigen Leistungen Entgegennahme der übersendeten Leistungsdaten des ANBAU (DA 11 nach REB) mitsamt den zugehörigen vollständigen und prüffähigen Unterlagen zur Leistungsfeststellung (Leistungsnachweis ist Aufgabe d…”
- 226FEI88209_1.4_Leistungen nach Baustellenverordnung (Ausfü.xlsm.pdf — “Leistungsbeschreibung Leistungen nach der Baustellenverordnung (während der Ausführungsphase) Die vorliegende Standardleistungsbeschreibung ist urheberrechtlich geschützt. Der DB AG steht an dieser Unterlage das ausschli…”
Login to view all answers and insights
Unlock tender brief for freeTENDER DOCUMENTS
DIRECTORY • 41 FILES
- 26FEI88209_1.4_Leistungen nach Baustellenverordnung (Ausfü.xlsm.pdf209 KBPDF
- 11-1 LBP- BÜ_Bad Liebenwerda-aktuell.pdf4.9 MBPDF
- 11-3-1_BuK_km_133.pdf1.3 MBPDF
and 34 other documents
Login to view and download all tender documents
Unlock documents for freeASK AI ABOUT THIS TENDER
Can a foreign company apply?
Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.
Login to ask more questions.