BLB NRW Duisburg / Mönchengladbach / Hochschule Niederrhein, Gebäude Spinnerei / Gebäudeautomation / 020-25-00384
Notice number: 00564160-2026
KEY INFORMATION
- Submission deadline
- • Sep 17, 2026
- Location
- 🇩🇪 Germany
- Contracting authority
- Bau- und Liegenschaftsbetrieb NRW Duisburg
- Accepted Languages
- German
- Tender type
- Works
- Contract Value
- Published date
- Aug 14, 2026
TENDER DESCRIPTION
This tender invites bids for comprehensive Building Automation (KGR 480) and Commissioning Management (IBM) services, crucial for the core renovation of the "Spinnerei" building at the Niederrhein University of Applied Sciences in Mönchengladbach. The scope encompasses detailed automation facilities, including data acquisition, control, regulation, communication with higher-level systems, and management functions, alongside extensive cable, line, and data transmission network installations, all conforming to standards such as DIN EN ISO 16484-3 and utilizing BACnet/Secure Connect automation stations, Layer 2 switches, and CAT 7A cabling. Key deliverables for commissioning management include integrated scheduling, factory and assembly planning, cross-trade functional testing, defect rectification, continuous task tracking, and comprehensive documentation via a Bauprojektmanagementplattform (BMP). The contract features an initial four-year term, commencing the day after construction work acceptance, with a possibility for a one-year extension. Bidders are required to submit declarations of turnover for the last three financial years and various certificates of good standing from…
TENDER BRIEF
The contract has a total duration of 4 years. The contract begins on the day following the acceptance of the construction work. The contract can be extended by one additional year if it is not terminated in writing at least three months before the expiration of the current term.
Sources
- 1020-25-00384_Instandhaltungsvertrag_Wartung_2018.pdf — “nach erfolgter Leistungserbringung jeweils nach erfolgter Leistungserbringung Die Erfüllung der berechtigten Entgeltforderungen erfolgt binnen 30 Tagen nach Rechnungszugang. Mängelansprüche Die Verjährungsfrist für Mänge…”
The core scope of work for this tender primarily involves Building Automation (Gebäudeautomation - KGR 480) and Commissioning Management (Inbetriebnahmemanagement - IBM), specifically for the core renovation of "Spinnerei".
The Statement of Work (SOW) summary and core deliverables include:
I. Building Automation (KGR 480):
- Automation Facilities (KGR 481):
- Recording of operational and fault messages, measurement, and count values.
- Issuing command and switching commands.
- Operational control, automatic and manual operation, control, and regulation.
- Communication with higher-level room automation devices and sub-systems.
- Displaying operational statistics.
- Functions according to DIN EN ISO 16484-3 for data acquisition, processing, and output.
- Services such as technical clarification, processing, input of addresses (user, plain text), characteristics, measuring ranges, units, parameters, program parts, programs, internal function markers and links.
- Testing, commissioning, fine-tuning, initial instruction of plant operators, and documentation.
- Physical input/output functions: Binary switching/actuating, analog output actuating, analog input measuring, and binary input reporting (all conforming to DIN EN ISO 16484-3).
- Processing functions: Monitoring fixed and sliding limit values, operating hour recording, command execution control, message processing, plant control, motor control, safety/frost protection control, P-regulation, PI-/PID-regulation, setpoint control/characteristic curve, continuous actuator output, arithmetic calculation, event-dependent switching, and time-dependent switching.
- Common input/output functions: Switching, actuating/setpoint, reporting, counting, and measuring.
- Automation Management (KGR 483):
- Management functions for communication input/output, communication block/file, event long-term storage, and database historization.
- Operating functions for graphics/plant display, dynamic overlay, event instruction text, and message parameterization.
- Cables, Lines, and Laying Systems (KGR 484):
- Preparation of cable laying, including creating cable lists, marking cable endpoints, and coordinating with the electrical contractor.
- Verification of the existing cable network, including checking cable endpoints, types, functionality, and documentation.
- Connection of various installation and control cables (e.g., halogen-free NHXMH-J 3x1.5RE, 3x2.5RE, 5x1.5RE; PVC-control cable F-CY-OZ 4x1; symmetrical installation cables J-H(St)H 2x2x0.8 Bd, 4x2x0.8 Bd; NYY-J 3x2.5RE; electrical connection 7x1mm² flexible).
- Data Transmission Networks (KGR 485):
- Installation of data connection boxes, Layer 2 switches (non-blocking 12 ports with DIN rail mounting), patch cables (CAT 7A up to 2m).
- Installation of horizontal/riser data cables (Kat.7A shielded 4x2xAWG23).
- Documentation of the TK-System (paper and data carrier).
- Measurement of Cu CL Link Ea and LWL OM4, including documentation of results as tables and graphics.
II. Commissioning Management (IBM):
- Contractor's (AN) Deliverables:
- Integration of the IBM schedule into the AN's construction schedule.
- Submission of factory and assembly planning.
- Cross-trade commissioning and functional testing.
- Delivery of necessary tools.
- Trial operation and defect rectification.
- Continuous maintenance of a task tracking list (open items list) with deadlines and status tracking, including references to relevant protocols and documents, to be submitted weekly.
- Compilation and provision of data sheets, performance data, plant and function descriptions, test certificates/approvals, and other relevant technical documentation to third parties as preliminary services during construction.
- Coordination and clarification of interfaces with other trades.
- Ongoing protocolling of functional tests, commissioning, and acceptance support.
- Providing input for the commissioning schedules and listing commissioning values for each function in the commissioning protocol.
- Accompanying the IBM manager during spot checks of commissioning activities.
- Joint Deliverables (AN, Client, General Planner, IBM Manager):
- Coordination of the interface catalog.
- Coordination of the trade relationship matrix.
- Execution and documentation of cross-trade functional testing.
- Coordination, Instruction, and Commissioning (KGR 489):
- Repeated instruction for operating and maintenance personnel (5 participants, 8 hours on-site).
- Hourly work by fitters (40h), control engineers (40h), and project managers (20h).
- Coordination of interfaces outside and within KGR 400.
- Participation in expert acceptance, providing approval and test documents, and having a responsible employee present.
Sources
- 1223_Aufgliederung_Einheitspreise_020-25-00384.pdf — “Angebotener Einheitspreis (Sp. $6+7+8+9$ Sonstiges 1 | 2 | 5 4 3 | 6 7 8 9 | | 10 01.03. 0010 | Managementfunktion Kommunikation Ein- /Ausgabefunktion | St 313 | | | 01.03. | Managementfunktion | 166 St | | | 0020 | Komm…”
- 2020-25-00384_Leistungsbeschreibung_Stand_260812.pdf — “Dienstleistungen--- Standardbeschreibung Funktionen GA Funktionen DIN EN ISO 16484-3, Massenermittlung dargestellt in GA-Funktionsliste, Beiblatt 070-5, für die Erfassung, Aufbereitung und Ausgabe von Informationen. Sie…”
Login to view all answers and insights
Unlock tender brief for freeTENDER DOCUMENTS
DIRECTORY • 38 FILES
- 2017_FGA_5_GR_KS--_DA_GEA_03_-_Gebaeudeautomation 1.pdf783 KBPDF
- 2017_FGA_5_GR_KS--_HE_GEA_02_-_Gebaeudeautomation 1.pdf1.6 MBPDF
- VVB 242 - Instandhaltung 12-2019.pdf65 KBPDF
and 31 other documents
Login to view and download all tender documents
Unlock documents for freeASK AI ABOUT THIS TENDER
Can a foreign company apply?
Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.
Login to ask more questions.
Unlock AI tender chat for freeUnlock your tender workflow
Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.