    Erneuerung EÜ Hanfbach - Bauüberwacher

    Notice number: ocds-mnwr74-07b99d46-3750-4c51-873a-b15300dcd930

    🇩🇪 GermanyDB InfraGO AG – Geschäftsbereich Fahrweg (Bukr 16)Services

    KEY INFORMATION

    Submission deadline
    Sep 14, 2026
    Location
    🇩🇪 Germany
    Contracting authority
    DB InfraGO AG – Geschäftsbereich Fahrweg (Bukr 16)
    Accepted Languages
    DEU
    Tender type
    Services
    Contract Value
    Published date
    Aug 14, 2026

    TENDER DESCRIPTION

    This tender seeks a Construction Supervisor for the Renewal of the Hanfbach Overpass, encompassing comprehensive technical and contractual construction supervision for traffic facilities, including railway operational services, safety supervision, waste management, environmental and landscaping oversight, and defect rectification. The role requires proficiency with AVA-Programm iTWO, GAEB-Format, Nachtragsplattform (NTP), SAP (including RACF), Workflow Betra-Antragerstellung, and DMS. Services are anticipated to commence by December 14, 2026, concluding with acceptance by July 2, 2027, although significant project phases, including a 2.5-month total closure, extend through July and August 2027 with follow-up work thereafter. Financial requirements mandate no insolvency, adherence to all statutory obligations, and strict compliance with sanctions lists, prohibiting direct or indirect involvement with specified sanctioned entities or Russian nationals/entities above defined thresholds. The contractor will be responsible for deliverables such as monthly status reports, invoice verification, and active claims management, but not for project control/management.

    TENDER BRIEF

    The contract timeline is as follows:

    Contract Start Date: The commencement of services by the contractor is either immediately after the order is placed or specifically on December 14, 2026. The execution of work on the construction site is scheduled to begin on December 14, 2026.

    Contract End Date: The completion for acceptance by the construction contractor is set for July 2, 2027.

    Total Duration: Based on the start date of December 14, 2026, and the completion for acceptance date of July 2, 2027, the primary contract duration is approximately 6.5 months. The contractor's activities generally begin with the construction execution and conclude with the unconditional acceptance of the final payment by the construction companies or the completion of assigned administrative tasks.

    Key Milestones and Phases:

    • Quality Gates (QG):
    • QG AN dates are to be established as milestones within 30 calendar days following the contract award.
    • QG 1 takes place at the actual start of performance.
    • QG 2 occurs during the performance phase, ideally at the midpoint of the contract duration. For contracts exceeding one year, multiple QG 2 meetings are planned.
    • Specific Project Phases/Closures (Sperrpausen):
    • October - December 2026: Initial clearing work, surveying, and other preparatory tasks.
    • December 14 - December 19, 2026: Clearing work, surveying, and other preliminary tasks (scheduled as 6x10h shifts).
    • January - February 2027: Surveying, other preparatory tasks, and the first block of unexploded ordnance investigation.
    • January 4 - January 9, 2027: Surveying, other preparatory tasks, and the first block of unexploded ordnance investigation (scheduled as 6x10h shifts).
    • Between 1st and 2nd block of unexploded ordnance investigation: Approximately 2 weeks are allocated for assessing the unexploded ordnance contamination.
    • January 25 - January 30, 2027: Second block of unexploded ordnance investigation, involving boreholes for the overpass (EÜ) and shoring (scheduled as 6x10h shifts).
    • February - March 2027: Cable work (LST, KT), provisional cable duct/cable auxiliary bridge, preparatory work for OLA, foundations for temporary tension masts, etc. (scheduled as 8x8h shifts).
    • March 30 - April 10, 2027: Cable work (LST, KT), provisional cable duct/cable auxiliary bridge, preparatory work for OLA, foundations for temporary tension masts, etc. (continuous operation).
    • April - May 2027: LST + 50 Hz + OLA + KT work, Hanfbach culvert construction, potential stiffening of existing vaults, removal of superstructure + switch, installation of bored piles through the existing structure (requiring a 1.75-month closure).
    • April 26 (5:00) - July 9, 2027 (21:00): Total closure (Totalsperrung) for 2.5 months for work in the streambed, specifically during times outside of migration and spawning periods.
    • July 9 (21:00) - July 11, 2027 (21:00): A 48-hour closure for "Belastung - Langsamfahrstelle La 70" (load - slow speed section 70 km/h).
    • August 29 - August 31, 2027: Six-week tamping (Qualitätsstopfung), including tamping of the switch connection (scheduled as 2x8h shifts).
    • Post-August 2027: Follow-up work (Nacharbeiten).

    Sources

    • 126FEI86642_0.0_Vertrag BauÜ_.pdf — “Bauleistungs-, Montage- und Haftpflichtversicherung). Es gilt der Wortlaut des Versicherungsvertra�ges. Alle Kosten, die dem AN durch seine Mitwirkung bei der Schadensabwicklung entstehen, sind mit der Vergütung abgegolt…
    • 226FEI86642_13.0_Quality Gates.pdf — “Festlegung im Projektterminplan und die Hinterlegung im Vertragsterminplan als entsprechende Meilensteine. Sollte im Vertrag kein Vertragsterminplan vereinbart sein, haben sich die Vertragsparteien in diesem Sinne über g…
    • 3EP_01.02_00_T_EÜHanfbach_ Sperrpausenbedarf.pdf — “6.1 LST + 50 Hz + OLA + KT Arbeiten Hanfbach verrohren Bestandsgewölbe ggf. aussteifen Ausbau Oberbau + Weiche Herstellung der Bohrpfähle durch den Bestand Sperrung Sperrung Sperrung Sperrung 1,75 Monate 6.2 Baugrubenaus…
    • 4EP_01.02_00_T_EÜHanfbach_ Sperrpausenbedarf_aktuell.pdf — “+ KT Arbeiten Hanfbach verrohren Bestandsgewölbe ggf. aussteifen Ausbau Oberbau + Weiche Herstellung der Bohrpfähle durch den Bestand Sperrung Sperrung Sperrung Sperrung 1,75 Monate 6.2 Baugrubenaushub + Herstellung Träg…

    • AVA-Programm iTWO
    • GAEB-Format
    • Nachtragsplattform (NTP)
    • SAP
    • RACF (as an additional condition for SAP)
    • Workflow Betra-Antragerstellung
    • DMS

    Sources

    • 126FEI86642_0.0_Vertrag BauÜ_.pdf — “Erfolgt die Auftragsbearbeitung unter Verwendung von DV-Anlagen des AN, sind, soweit nachste�hend nichts anderes bestimmt ist, die anzuwendenden Programme vor Beginn der Bearbeitung mit dem AG abzustimmen. Datenträger un…
    • 226FEI86642_5.0_ZVB-EDV.pdf — “eingesetzt. Für SAP gilt zusätzlich RACF; für die Betra-Antragerstellung gelten zusätzlich die Bedingungen des Workflow Betra-Antragerstellung; für DMS gelten die Regelungen der GBV. (2) Für die vom Dritten eingestellten…

    Login to view all answers and insights

    Unlock tender brief for free

    TENDER DOCUMENTS

    DIRECTORY • 126 FILES

    • BBPneo_ Baubetriebsplan_Hanfbach_20.07.2026.pdf
    • Thumbs.db
    • 26FEI86642_1.7_Abfallmanagement.xlsm.pdf

    and 119 other documents

    Login to view and download all tender documents

    Unlock documents for free

    ASK AI ABOUT THIS TENDER

    You

    Can a foreign company apply?

    Riko

    Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.

    Login to ask more questions.

    Unlock AI tender chat for free

    Unlock your tender workflow

    Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.

    First monitor on Day 1All features included in trialNo credit card required

    You may also be interested in

    Similar tenders