    This tender solicits proposals for external site management, construction management, and construction supervision services for the replacement new construction of the Ruhr Bridge structure (Ersatzneubau Bauwerk Ruhrbrücke). The comprehensive scope includes site and planning management, environmental and logistics management (including soil logistics and waste officer appointment), demolition of existing elements, construction of new inlet structures, and prefabricated box girder bridge superstructures, alongside ground investigation, UXO clearance, and technical engineering with permit acquisition. The project mandates strict adherence to Building Information Modeling (BIM) methodologies, utilizing a BIM collaboration system (DESITE with "EPLASS Edition") and Thinkproject CDE INFRASTRUCTURE (EPLASS) as the Common Data Environment, in accordance with DIN-19650, Autobahn GmbH file naming conventions, and relevant DIN standards and federal regulations. Expected to commence in November 2026 and conclude by December 31, 2031, over approximately 5.5 years, this engagement requires proof of professional liability insurance with coverage of €3.00 million for personal injury and €5.00…

    TENDER BRIEF

    The contract timeline is as follows:

    The beginning of the execution is slated for no later than 6 working days after the contract award. The overall assignment period for external construction supervision is expected to commence in November 2026. The contractor's services are set to begin with the official construction start meeting.

    The completion of the execution is scheduled for no later than December 31, 2031. The planned conclusion of the contractual measure, specifically the external construction supervision, is in the 3rd quarter of 2031. The contractor's services will conclude with the successful review and approval of the final invoice for the measure.

    The total duration of the project is approximately 5.5 years.

    Key milestones and phases include:

    • Besprechungstermine (meeting dates) annually from 2027 to 2031.
    • Review of existing documents ("Prüfung Bestandsunterlagen").
    • Transport of concrete cubes to the testing institute in calendar year 2027.
    • Tendering of the noise barrier measure in the 3rd quarter of 2029, with construction in 2030.
    • Review and processing of final invoices ("Schlussrechnungen") for the construction contract "Replacement new construction of the noise barrier on the Ruhr bridge structure" in calendar year 2031.
    • The contractor is required to submit a detailed construction schedule/timeline within 4 calendar weeks after contract award, reflecting the contractually agreed dates, and to provide a milestone trend analysis (MTA). The construction schedule must be updated digitally every two weeks with a target-actual comparison.

    Sources

    • 1HVA_F_StB_Vertragsbedingungen.pdf — “HVA F-StB Vertragsbedingungen Bezeichnung der Leistung: A-07731-40 A3, Ersatzneubau Bauwerk Ruhrbrücke 02-26-5041 Externe BÜ ENB BW Ruhrbrücke Vertragsbedingungen 1. Besondere Vertragsbedingungen 1.1 Termine und Fristen…
    • 202-26-5041_LB Externe BÜ_ENB BW Ruhrbrücke.pdf — “erfolgt unverzüglich nach Auftragserteilung, spätestens jedoch 10 Kalendertage nach Vertragsschluss. Der reguläre Gesamteinsatzzeitraum der ÖBÜ beginnt voraussichtlich im November 2026 und endet mit dem planmäßigen Absch…
    • 302-26-5041_LPV_Externe BÜ.pdf — “| 00.07. | Besprechnungstermine 2027 | 00.08. | Besprechnungstermine 2028 | 00.09. | Besprechnungstermine 2029 | 00.10. | Besprechnungstermine 2030 | 00.11. | Besprechnungstermine 2031 | 00.12. | Prüfung Bestandsunterlag…
    • 42.01_BB_ENB BW Ruhrbrücke_Bauvertrag 02-25-0067.pdf — “(vgl. BVB) sind darzustellen. Erfolgt die Bauausführung nach Teilabschnitten, sind diese auch im Bauablaufplan darzustellen. Bei Notwendigkeit sind Verkehrsführungs- und Sperrphasen sowie Pufferzeiten anzugeben. Während…

    The core scope of work for this tender primarily involves the Replacement New Construction of the Ruhr Bridge structure (Ersatzneubau Bauwerk Ruhrbrücke).

    The high-level summary of the Statement of Work and core deliverables includes:

    • Site Management and Planning: This encompasses the creation and monthly updating of a Construction Site Plan (BE-Plan) and Construction Schedule (Bauzeitenplan) for all new construction phases, including the demolition of the existing structure (TBW Ost) and modification of retaining wall BW 14, along with safety measures for public traffic and a construction road concept. It also includes general construction site setup with necessary equipment and tools.
    • Water Management: Implementation of surface water drainage (Tagwasserbeseitigung) at BAB 3 to protect work areas and materials from rainwater.
    • Environmental and Logistics Management: Developing and updating a soil logistics concept for sampling, excavation, transport, storage, loading, processing, and installation of soil and dredged material. Additionally, appointing a waste officer to oversee all disposal and reuse processes, including planning and monitoring waste separation, heap formation, and sampling.
    • Documentation and Review: Reviewing, structuring, and technically examining existing project documents (drawings, plans, data) for accuracy and completeness, including plausibility checks against on-site conditions and identifying data gaps. This also involves archiving and handing over documents as specified by the client.
    • Specific Construction Activities: This involves various tasks such as formwork and concrete works, including the production of concrete for blinding layers and formwork for concrete components.
    • Replacement of Inlet Structures (Ersatzneubau Einleitungsbauwerke): This includes demolition of existing reinforced concrete inlet structures, removal and application of topsoil, grass seeding, construction of pipe trenches and excavation pits, delivery and compaction of building materials, construction of steel sheet piling with bracing, filling existing drainage pipes, constructing concrete drainage pipes, building precast shafts (TG-1A and TG-2A), and all associated formwork, reinforcing steel installation, and reinforced concrete production.
    • Bridge Superstructure: The bridge superstructures will utilize prefabricated, walkable box girders with reinforced concrete deck slabs, some incorporating precast elements, designed as a continuous beam system.
    • Coordination and Documentation: Overall coordination of specialist models through regular consolidation, quality checks (data, information, collision detection), and systematic conflict resolution using cloud-based issue management. This also covers model-based documentation of construction-related information (e.g., documents, test protocols, delivery notes, material data, maintenance regulations) on a common data environment (CDE).
    • Surveying: Implementation of a measurement program for the replacement new construction on the west side.
    • Ground Investigation and Clearance: Conducting inclined exclusion/probe drillings (d=120 mm) to depths of 8m in specific areas, backfilling boreholes, and documenting the process. Marking and electronically measuring borehole starting points for exploratory drilling. Performing visual Unexploded Ordnance (UXO) clearance, which includes full-surface inspection for UXO on the ground surface, checking vegetation, recovering manageable UXO, securing unmanageable UXO, and removing other disruptive objects.
    • Technical Engineering and Permits: Technical processing for all construction aids, installations, and scaffolding according to DIN 18451 and client specifications, including obtaining all necessary public and legal permits and approvals for the new replacement construction (Teilbauwerk Ost). This also covers technical planning and execution for modifying or relocating the escape staircase at retaining wall BW 14, Block 14-1 and 14-2, including workshop planning and permit acquisition.
    • Existing Document Delivery: Producing and delivering existing documents as per ZTV-ING, Part 1, Section 2 for Teilbauwerk Ost.

    Sources

    • 12.02_LV_ENB BW Ruhrbrücke_Bauvertrag 02-25-0067.pdf — “02-25-0067 LV: | 02-25-0067 A 3, ENB BW Ruhrbrücke Ersatzneubau Bauwerk Ruhrbrücke Ersatzneubau Bauwerk Ruhrbrücke OZ | AE StL-Nr Menge EP in EUR GB in EUR 01.07.0004. | 24.802/040.09.22 ΤΑ 1,00 Psch XXXXXX,XX Bodenlogis…
    • 22.01_BB_ENB BW Ruhrbrücke_Bauvertrag 02-25-0067.pdf — “Abstumpfungsmaßnahme durchführen. | Ersatzneubau Einleitungsbauwerke ca. $21~m^{3}$ | vorhandene Bauliche Anlage aus Stahlbeton (Einlaufbauwerk Tiefgebiet) abbrechen ca. $13~m^{3}$ | vorhandene Bauliche Anlage aus Stahlb…
    • 302-26-5041_LPV_Externe BÜ.pdf — “auf der Außenkappe vom Teilbauwerk Ost) im Kalenderjahr 2030. 1,00 Psch XXXXXX,XX | | Sichtung&Prüfung Bestandsunterlagen Sichtung, strukturierte Erfassung und fachtechnische Prüfung der vorhandenen Bestandsunterlagen (B…

    Login to view all answers and insights

    Unlock tender brief for free

    TENDER DOCUMENTS

    DIRECTORY • 113 FILES

    • Information_Datenschutz.pdf
    • 2.10_ENB BW Ruhrbrücke_Pfeiler A60_Schnitte und Ansichten.pdf
    • 2.13_ENB BW Ruhrbrücke_Neubau TBW West_GR_LS.pdf

    and 106 other documents

    Login to view and download all tender documents

    Unlock documents for free

    ASK AI ABOUT THIS TENDER

    You

    Can a foreign company apply?

    Riko

    Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.

    Login to ask more questions.

    Unlock AI tender chat for free

    Unlock your tender workflow

    Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.

    First monitor on Day 1All features included in trialNo credit card required

    You may also be interested in

    Similar tenders