    Grossspeichersystem

    Notice number: 00533580-2026

    🇨🇭 SwitzerlandPolitische Gemeinde Vilters-Wangs (Technische Betriebe)Goods

    KEY INFORMATION

    Submission deadline
    Sep 11, 2026
    Location
    🇨🇭 Switzerland
    Contracting authority
    Politische Gemeinde Vilters-Wangs (Technische Betriebe)
    Accepted Languages
    German
    Tender type
    Goods
    Contract Value
    Published date
    Aug 3, 2026

    TENDER DESCRIPTION

    This tender invites proposals for the delivery, installation, and commissioning of a turnkey Battery Energy Storage System (BESS), complete with all individual components, including import logistics, and a comprehensive 10-year service and warranty agreement. The mandatory scope encompasses cabling, transformers designed for 16kV/20kV step-up with galvanic isolation, and NIV registration, with performance guarantees including at least 5.0 MWh usable energy capacity and 1.3 MW usable active power for ten years post-acceptance. Key technical requirements include a robust control platform, Battery Management System (BMS), IT security concept, containerized solution, Primary Frequency Control (PFC), Swissgrid metering, and provisions for future capacity expansion. The contract timeline is structured around flexible milestones relative to "Zeitpunkt N" (permit validity and order placement), with post-acceptance maintenance extending over at least ten years. Tenderers must demonstrate sound financial standing, confirming full payment of taxes and social security contributions, and declaring any active debt collection or bankruptcy proceedings.

    TENDER BRIEF

    The contract timeline is structured around a flexible "Zeitpunkt N" (Time N), which is defined as the date when all required official permits for the work are legally binding and the client has placed the individual order. Specific fixed contract start or end dates are not provided. The total duration is not explicitly stated as a fixed period but is outlined through a series of milestones relative to "Zeitpunkt N".

    Key milestones and phases include:

    • Zeitpunkt N: Receipt and legal validity of official permits and placement of the individual order.
    • N + Weeks:
    • Delivery of documents relevant for building permits and client-side services (final version).
    • Delivery of documents relevant for grid connection/grid feedback readiness (final version).
    • Completion of client-side services at the work location and notification for inspection.
    • Visual inspection of client-side services at the work location.
    • Complete installation of the work.
    • Readiness for grid feedback and notification.
    • Visual inspection of grid feedback readiness.
    • Declaration of readiness to conduct joint commissioning tests.
    • Completion of commissioning of the entire work.
    • Training of the client's employees.
    • Delivery of complete work documentation.
    • Final acceptance.

    Additionally, there is a maintenance contract mentioned, with payments scheduled 96 months (8th year) and 108 months (9th year) after successful final acceptance, indicating a potential post-acceptance period of at least 10 years for the maintenance contract.

    Contract start date, end date, and total duration as fixed calendar dates are not explicitly stated.

    Sources

    • 1Kap 04 Werkvertrag V5.pdf — “dieser Daten). Als Woche(n) gelten 7 (sieben) Kalendertage bzw. das Mehrfache davon. Sie beginnt mit dem das Ereignis auslösenden folgenden Wochentag. ii. Fristenstillstand: Termine bzw. Fristen (abgesehen von Zahlungsfr…
    • 2Kap 04 Werkvertrag V5 Schwarm.pdf — “(einschliesslich dieser Daten). Als Woche(n) gelten 7 (sieben) Kalendertage bzw. das Mehrfache davon. Sie beginnt mit dem das Ereignis auslösenden folgenden Wochentag. ii. Fristenstillstand: Termine bzw. Fristen (abgeseh…

    The core scope of work for this tender involves the delivery of a turnkey, complete, perfectly functioning, and commissioned Battery Energy Storage System (BESS). This includes the import and delivery of all individual components to the construction site, encompassing packaging, insurance, customs, and necessary permits. The contractor is responsible for confirming the completeness of the delivery in writing.

    The Statement of Work (SOW) is detailed across several appendices and encompasses the following key deliverables and responsibilities:

    • Installation Division of Responsibilities (Anhang C-1): Defining tasks for both the contractor and client until final acceptance.
    • Services Division of Responsibilities (Anhang C-2): Outlining tasks for both parties after final acceptance.
    • System Specifications (Anhang C-3): Providing essential specifications and key metrics of the BESS.
    • Interface Specifications (Anhang C-4): Defining interfaces related to the client's scope of supply, such as the grid connection.
    • Site Commissioning Testing (Anhang C-5): Describing the required commissioning tests.
    • Remote Monitoring (Anhang C-6): Detailing the remote access concept for the system.
    • Spares List (Anhang C-7): Listing necessary spare parts.
    • Definitions for completion of client-side services, installation complete, readiness for grid feedback, and completion of commissioning (Anhang C-8 to C-11): These documents are to be developed after the award.
    • Final Acceptance Metrics (Anhang C-12): Including availability criteria, such as available power >= 99% and an availability factor >= 96%, to be met without human intervention for three weeks prior to final acceptance.

    The mandatory scope of the offer explicitly includes:

    • Cabling between the battery-inverter/transformer and NS distribution.
    • Transformers (battery transformers and auxiliary transformer with housing) designed to step up to 16kV/20kV and provide galvanic isolation.
    • NIV registration and acceptance.

    The contractor is also responsible for guaranteeing a usable energy capacity of at least 5.0 MWh for 10 years after final acceptance, with the possibility of replacing or adding battery modules to maintain this capacity. A usable active power of at least 1.3 MW is also required. Key components to be supplied include the complete battery system, complete inverters, and complete transformers. Performance guarantees also include a guaranteed State of Health (SOH), Round Trip Efficiency DC, and available energy DC, along with maintenance.

    Sources

    • 1Kap 04 Werkvertrag V5 Schwarm.pdf — “der Parteien im Zusammenhang mit der Werkerstellung sind dem Anhang D-1: Installationsverantwortungsmatrix zu entnehmen. Der Unternehmer schuldet dem Besteller ein schlüsselfertiges, vollständiges, einwand- frei funktion…
    • 2Kap 04 Werkvertrag V5.pdf — “BESS). Die Pflichten der Parteien im Zusammenhang mit der Werkerstellung sind dem Anhang D-1: Installationsverantwortungsmatrix zu entnehmen. Der Unternehmer schuldet dem Besteller ein schlüsselfertiges, vollständiges, e…
    • 3Kap 02 Technical requirements BESS V5.pdf — “to components within the suplier's scope of supply (engineering, construction management, foundations) Χ. NIV registration and acceptance. xi. 6.2 i. 6.3 i. ii. iii. Transformers (comprising battery transformers and auxi…
    • 4Kap 06 Preisblatt V5.pdf — “für die Basisleistungen Zeitpunkt | Anteil vom Nettopreis: Bei Bestellung | Bei Lieferung | Nach erfolgreicher Abnahme | Angaben zur Lösungsfindung Schlüsselargumente, die für den Anbieter sprechen Alternative Vorschläge…

    Login to view all answers and insights

    Unlock tender brief for free

    TENDER DOCUMENTS

    DIRECTORY • 13 FILES

    • Kap 07 Referenzen V5.pdf
    • Kap 05 Angaben zur Unternehmung V5.pdf
    • Kap 04 Werkvertrag V5 Schwarm.pdf

    and 6 other documents

    Login to view and download all tender documents

    Unlock documents for free

    ASK AI ABOUT THIS TENDER

    You

    Can a foreign company apply?

    Riko

    Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.

    Login to ask more questions.

    Unlock AI tender chat for free

    Unlock your tender workflow

    Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.

    First monitor on Day 1All features included in trialNo credit card required

    You may also be interested in

    Similar tenders