Published
Marché de maîtrise d'oeuvre pour la Construction neuve d'une résidence intergénérationnelle de 70 logements en Hors Site (filière sèche bois et biosourcée) à Marseille (La Savine - 13015)
Notice number: 00524502-2026
KEY INFORMATION
- Submission deadline
- • Sep 15, 2026
- Location
- 🇫🇷 France
- Contracting authority
- SA ERILIA, société à mission
- Accepted Languages
- French
- Tender type
- Services
- Contract Value
- Published date
- Jul 29, 2026
TENDER DESCRIPTION
This tender seeks comprehensive project management services for the new construction of an intergenerational residence in Marseille, comprising 70 collective dwellings, a 100 m² common room, and 70 underground parking spaces, with no demolition planned. The core scope encompasses a base mission with additional services including preliminary design (ESQ, AVP, PRO), G2 and G4 studies, tender document preparation (DCE), contract award assistance (ACT), partial execution studies (EXE), verification (VISA), site supervision (DET), project coordination (OPC), and after-sales management (AOR) covering a 12-month Perfect Completion Guarantee (GPA). Key technical requirements mandate off-site construction, a strong focus on the wood industry and prefabrication, extensive use of biosourced materials to achieve Label Bâtiment Biosourcé niveau 2, and compliance with RE2020 level 2025 and BDM Argent certification. The contract has a provisional duration of 48 months, segmented into 12 months for studies, 24 months for works, and 12 months for the GPA, with works anticipated to commence in the second half of 2027. Financial requirements include submitting annual turnover data for the last…
TENDER BRIEF
Question: What is the contract timeline?
Context: Contract start date, end date, total duration, and any key milestones or phases mentioned. Return null if not stated.
The contract execution period commences upon the notification of the contract.
The provisional total duration of the market is 48 months, broken down into key phases:
- Studies: 12 months
- Works: 24 months
- Perfect Completion Guarantee (GPA): 12 months
Within the studies phase, specific deadlines for various stages are:
- Sketch studies: Four weeks
- Preliminary design studies: Eight weeks (including EAPS: Four weeks and EAPD: Four weeks)
- Project studies: Four weeks
- Preparation of tender documents: Two weeks
- ACT: Two weeks
- VISA: Two weeks
The provisional start date for the works is the 2nd semester of 2027.
Sources
- 1CCA MOE LA SAVINE.pdf — “sera communiqué par l'architecte MOE pour les marchés de type TRAVAUX et par Erilia ou téléchargeable directement sur la plateforme pour les marchés d'HONORAIRES. Lors de la déclaration de votre situation, vous pourrez (…”
- 2AE MOE LA SAVINE.docx — “partielle (cadre de décomposition quantitatif), VISA, DET, OPC, AOR comprenant le suivi de la GPA (12 mois). Durée prévisionnelle du marché: 48 mois (12 mois études + 24 mois travaux + 12 mois GPA). Label visé : BDM Arge…”
The core scope of work for this tender includes a base mission with complementary services: ESQ (Esquisse), AVP (Avant-Projet), PRO (Projet), G2 and G4 studies, DCE (Dossier de Consultation des Entreprises), ACT (Assistance pour la passation des Contrats de Travaux), partial EXE (Execution) with a quantitative breakdown framework, VISA, DET (Direction de l'Exécution des Travaux), OPC (Ordonnancement, Pilotage et Coordination), and AOR (Assistance aux Opérations de Réception) which comprises a 12-month follow-up of the GPA (Perfect Completion Guarantee).
The provisional duration of the market is 48 months, broken down into 12 months for studies, 24 months for works, and 12 months for GPA. The project aims for a "BDM Argent" label.
Key deliverables and the Statement of Work summary include:
- Estimation of work costs by trade.
- Indicative estimation of energy consumption for the structures.
- General and detailed plans, including those for housing, common areas, specific detailed zones, roofs/terraces, facades, and cuts.
- Equipment plans detailing sanitary, lighting, heating, technical and household equipment, and technical ducts.
- Production of the Cahier des Clauses Techniques Particulières (CCTP), which specifies the breakdown of work into lots, detailed descriptive estimates, technical prescriptions, and information on subsoil occupation.
- A comprehensive calendar for all services.
- A price breakdown framework by trade and price item.
- For rehabilitation projects, the production of a descriptive state summarizing works requiring replacement, repair, or compliance, along with a memo presenting argued solutions.
- Proposition, justification, and definition of constructive principles, technical solutions (especially for biosourced materials), and materials, including calculation of biosourced content.
- Ensuring compliance with requirements from administrative services (e.g., firefighters) and concession services.
- Preparation of building permit application documents until approval is obtained.
- Establishment of a provisional work schedule.
- For rehabilitation, creation of visual documents for tenants such as exterior/interior perspectives, simplified housing plans, and explanatory diagrams.
- A memo detailing physical data, chosen urbanistic and architectural solutions, surface area breakdowns, technical solutions (including reference documents for biosourced solutions and content calculation), a summary description of works and materials, execution deadlines, and compliance with urban planning, fire protection, and occupational safety regulations.
- Monitoring the integration of biosourced solutions and updating the carbon study (RSEE.XML file) during the execution phase and at the end of the construction.
- Assistance to the contracting authority in subscribing to construction insurance and providing consultative advice during the approval of candidate companies.
- Control of the implantation plan established by the contractor's surveyor and providing opinions on subcontractors.
Sources
- 1AE MOE LA SAVINE.docx — “partielle (cadre de décomposition quantitatif), VISA, DET, OPC, AOR comprenant le suivi de la GPA (12 mois). Durée prévisionnelle du marché: 48 mois (12 mois études + 24 mois travaux + 12 mois GPA). Label visé : BDM Arge…”
- 2CCA MOE LA SAVINE.pdf — “confiées à la maîtrise d'œuvre (mission de base complémentaires): ESQ, AVP, PRO, études G2 et G4, DCE, ACT, EXE partielle (cadre de décomposition quantitatif), VISA, DET, OPC, AOR comprenant le suivi de la GPA (12 mois).…”
- 3CCT MOE LA SAVINE.pdf — “Consultation. 4. L'estimation du coût des travaux par corps d'état Cette évaluation comprend toutes les dépenses afférentes à l'exécution des ouvrages (bâtiments équipés, raccordements, et fondations) suivant le cadre de…”
Login to view all answers and insights
Unlock tender brief for freeTENDER DOCUMENTS
DIRECTORY • 13 FILES
- AE MOE LA SAVINE.docx58 KBDOCX
- 03 251014-S-P-MLS-échanges fonciers A3H 2500°+projet PU.pdf639 KBPDF
- AWS-Achat_depot-sans-signature.pdf572 KBPDF
and 6 other documents
Login to view and download all tender documents
Unlock documents for freeASK AI ABOUT THIS TENDER
Can a foreign company apply?
Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.
Login to ask more questions.
Unlock AI tender chat for freeUnlock your tender workflow
Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.