Mission d'assistance à maîtrise d'ouvrage technique pour les travaux de mise en accessibilité des lycées de la Région Occitanie, secteur Est (départements de l'Aveyron, de l'Hérault, du Gard, de l'Aude, de la Lozère et des Pyrénées Orientales)
Notice number: 00511359-2026
KEY INFORMATION
- Submission deadline
- • Sep 10, 2026
- Location
- 🇫🇷 France
- Contracting authority
- Spl arac occitanie
- Accepted Languages
- French
- Tender type
- Services
- Contract Value
- Published date
- Jul 23, 2026
TENDER DESCRIPTION
This tender seeks a Technical Project Management Assistance mission to support the contracting authority in managing and deploying accessibility works across high schools in the Occitanie Region, East sector. The core scope encompasses comprehensive diagnostics for lighting, accessibility, and elevator systems, strategy elaboration, prior declarations, work authorizations, assistance with construction contracts (ACT), technical support during the work phase, accessibility certifications, Ad'Ap synthesis, and design assistance. Required technical expertise includes multi-trade building engineering, elevator installation engineering, construction economics, project management (OPC), and asbestos (SS3 technical supervision) certification, utilizing an exchange platform and IFC file visualization. The contract spans a total of four years, comprising a six-month study period and a two-year work period, with specific diagnoses to be completed within three weeks of submission; financial standing requires annual turnover for the last three available financial years.
TENDER BRIEF
The contract has a total duration of 4 years. The overall study period is 6 months, and the work period is 2 years. Specific tasks include an accessibility diagnosis and a lighting diagnosis, both to be completed within 3 weeks from submission. The validity period for offers is 180 days from the deadline for their submission. The contract mentions distinct phases, including an "études" (studies) phase and a "travaux" (works) phase. Services will be performed according to purchase orders that will specify execution times. There is also a mention that subsequent markets can be concluded for a period not exceeding three years from the notification of the present market. A specific contract start date or end date is not explicitly stated.
Sources
- 1A0-AE mission AMOT.docx — “dans chaque annexe constitue le montant maximal de la créance que le sous-traitant concerné pourra présenter en nantissement. Chaque annexe constitue une demande d'acceptation du sous-traitant concerné et d'agrément des…”
- 2AWS-MPI-1852295-RC.docx — “candidature Acte d’engagement Tableau de répartition des honoraires BPU et DQE Acte Spécial Sous-traitance Charte des données informatiques CCTP Liste des lycées BPU/DQE Modèle de versement d'acompte Manuel pour une meil…”
- 361037106 RC mission AMOT.docx — “candidature Acte d’engagement Tableau de répartition des honoraires BPU et DQE Acte Spécial Sous-traitance Charte des données informatiques CCTP Liste des lycées BPU/DQE Modèle de versement d'acompte Manuel pour une meil…”
- 4B0-CCAP.docx — “l’exécution des prestations au terme de la phase études ainsi qu’au terme de chacune des phases techniques de la réalisation du chantier. Par dérogation à l’article 20 du CCAG-PI, l’arrêt de la prestation au terme de la…”
The core scope of work for this tender involves a range of missions primarily focused on diagnostics, strategy elaboration, and technical assistance for accessibility, lighting, and elevator systems, within the context of renovation.
The key missions and their associated activities/deliverables are:
- Diagnostic éclairage (Lighting Diagnostic): This is a firm mission.
- Diagnostic accessibilité (Accessibility Diagnostic): This firm mission includes site visits to categorize interventions for strategy elaboration. Expected deliverables per site include a synthesis sheet detailing specificities, updated provisional work costs (recurrent, architectural), a site plan, recap of complementary studies, site constraints, contact information of attendees, detailed program by work type with measurements, quantitative, qualitative and functional objectives, photos, work cost estimation, recommendations for sequencing and planning, and identification of required authorizations (e.g., building permit, prior declaration, work authorization, derogation requests).
- Expertise ascenseur (Elevator Expertise): This firm mission aims to establish a complete state of the elevator, diagnose maintenance, analyze installation conformity, and specify necessary works to ensure regulatory compliance, improve reliability and safety, adhere to norms, and optimize user experience. Deliverables include an expertise report covering installation characteristics, equipment dates, photos, maintenance diagnostic, conformity (including SAE law), and a synthesis with work estimations (regulatory, reliability, recommendations, aesthetic). It also includes updating existing elevator expertise.
- Elaboration de la stratégie (Strategy Elaboration): Following diagnostics, this firm mission involves establishing the deployment strategy and work program, including categorizing diverse works (excluding lighting and elevators) into types such as "Travaux récurrents" (recurrent works like handrails, handles that do not require design studies).
- Déclaration préalable et autorisation de travaux (Prior Declaration and Work Authorization): This is a firm mission.
- ACT (Assistance aux Contrats de Travaux): This is a firm mission, involving stages like DCE (30%), analysis of offers (30%), and market finalization (40%).
- Assistance technique en phase travaux (Technical Assistance during Work Phase): This is a firm mission.
- Attestations d'accessibilité (Accessibility Certifications): This is a firm mission.
- Synthèse Ad'Ap (Ad'Ap Synthesis): This is a firm mission.
- Aide à la conception (Design Assistance): This is a firm mission.
- Vacations: This is a firm mission.
The project also references various phases such as ESQ, APS, APD, PRO, VISA, DET, and AOR. The overall duration of the market is 4 years, with a global study period of 6 months and a work period of 2 years. The category of work is renovation.
Sources
- 1A1 AE Ann 1 Répart hono par co-traitants.xlsx — “au MO en cas de réclamation),,0,,,,,,,,,, 7.2.9,AOR (20% à la remise des DOE + 40% à l'accusé de réception du dernier procès-verbal de levé de toute les réserves + 20% à la notification du décompte général définitif des…”
- 2B0-CCAP.docx — “à maîtrise d’ouvrage comprendra les éléments suivants : Diagnostic éclairage, Diagnostic accessibilité, Expertise ascenseur, Elaboration de la stratégie Déclaration préalable et autorisation de travaux, ACT, Assistance t…”
- 3A0-AE mission AMOT.docx — “dans chaque annexe constitue le montant maximal de la créance que le sous-traitant concerné pourra présenter en nantissement. Chaque annexe constitue une demande d'acceptation du sous-traitant concerné et d'agrément des…”
- 4CCTP AMO Accessibilite vague 3.docx — “la/les visite(s) de site. L’objectif est de catégoriser par nature d’intervention ces travaux en phase élaboration de la stratégie. Réunion de restitution Rendus attendus : Pour chaque site, le titulaire réalisera une fi…”
- 5D-BPU DQE.xlsx — “m2,2,0,2,0,2,0,2,0,,0,0 ,,1.2.2 1000 m2 pour un site de plus 5000 m2,,0,,0,8,0,1,0,,0,0 ,,1.2.3 1000 m 2 pour un site de plus de 10 000 m2,1,0,,0,,0,1,0,,0,0 ,,1.2.4 1000 m 2 pour un site de plus de 15 000 m2,,0,,0,16,0,…”
Login to view all answers and insights
Unlock tender brief for freeTENDER DOCUMENTS
DIRECTORY • 37 FILES
- DC1.docx80 KBDOCX
- OCC_04_Fiche_Accueil_v1_210830.pdf1.1 MBPDF
- OCC_09_Fiche_Ressenti_Ambiances_v1_210830.pdf1.1 MBPDF
and 30 other documents
Login to view and download all tender documents
Unlock documents for freeASK AI ABOUT THIS TENDER
Can a foreign company apply?
Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.
Login to ask more questions.
Unlock AI tender chat for freeUnlock your tender workflow
Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.