Mission de maîtrise d'oeuvre : RÉHABILITATION RÉSERVOIR ET REFONTE POMPAGE VILLEJEAN - GALLETS
Notice number: 26-72104
KEY INFORMATION
- Submission deadline
- • Oct 9, 2026
- Location
- 🇫🇷 France
- Contracting authority
- Collectivité Eau du Bassin Rennais
- Accepted Languages
- French
- Tender type
- Services
- Contract Value
- Published date
- Jul 20, 2026
TENDER DESCRIPTION
This tender seeks a project management mission for the rehabilitation of the Villejean - Gallets reservoir and pumping system overhaul. The scope encompasses a firm tranche covering diagnostic analysis, preliminary and detailed project design, assistance with contractor procurement and contract finalization, works execution management (DET, OPC), and acceptance operations. Additionally, optional tranches include various complementary studies such as 3D scanning, structural, asbestos, lead, geotechnical, energy performance, and acoustic diagnostics, alongside camera inspection and technical control. The contract has an indicative total duration of four years, comprising one year for studies, two years for works, and one year for warranty, with an estimated works financial envelope of €1,700,000 HT, excluding specific waterproofing. Tenderers must provide indications concerning their general annual turnover over three years, with electronic submissions requiring specified formats (e.g., .pdf, .docx, .dwg) and eIDAS-compliant electronic signatures.
TENDER BRIEF
The contract has an indicative total duration of 4 years, which includes 1 year for studies, 2 years for works, and 1 year for warranty.
Key milestones and phases include:
- Diagnostic: 3 months for realization, starting from the contract notification, followed by 6 weeks for validation by the contracting authority (MOA).
- Avant-Projet (AVP): 4 months for realization, starting from the date specified on the service order (OS), followed by 6 weeks for validation by the MOA.
- Projet (PRO): 3 months for realization, starting from the date specified on the OS, followed by 6 weeks for validation by the MOA.
- Dossier de Consultation des Entreprises - Acte d'Engagement (DCE-ACT):
- Realization of DCE: 4 weeks from the OS date, with 2 weeks for validation by the MOA.
- Verification of candidatures and offers, and assistance with negotiation, including establishing the provisional offer analysis report (RAO): 2 weeks from the transmission of offers to the contracting authority's representative (MOE), with 2 weeks for validation by the MOA.
- Realization of the definitive RAO and assistance with contract finalization: 2 weeks from the transmission of negotiation responses to the MOE, with 2 weeks for validation by the MOA.
- VISA: 2 weeks for presenting documents to be endorsed, followed by 2 weeks for validation by the MOA.
- Direction de l'Exécution des Travaux (DET):
- Notification of service order (OS) to the entrepreneur: 7 calendar days from the request email, or 2 days in case of urgency.
- Drafting and dissemination of site meeting reports: 2 days after the site meeting.
- Tranche Ferme (TF):
- Opinion on subcontracting requests: 5 calendar days from receipt of the request, or 7 calendar days if received via Chorus.
- Verification of monthly contractor statements: 7 calendar days from receipt of the request via Chorus.
- Verification of final contractor statements: 20 calendar days from receipt of the request via Chorus.
- Instruction of claims: 15 calendar days from receipt of claims for realization, with 2 weeks for validation by the MOA.
- Assistance aux Opérations de Réception (AOR):
- Proposal for reception (EXE 5): 5 calendar days from the Operations Preliminary Meeting (OPR).
- Submission of the lifting of reservations report (EXE 8 and 9): 5 calendar days from the reservations lifting meeting.
- Verification of the as-built documents (DOE): 1 month from receipt of the DOE by the MOE, with 2 weeks for validation by the MOA.
- Document synthesis: 21 calendar days from the OS date, with 2 weeks for validation by the MOA.
- TF and Optional Tranches (TO 1 to 8):
- Document revisions: 15 calendar days from the MOA's request email, with 2 weeks for validation by the MOA.
The provisional financial envelope was established based on the program of operations as of 28/01/2026.
Sources
- 12_CCP_SBV_MOE-pompages.pdf — “ne sont pas toutes levées à la fin de cette période. Sa durée indicative est de 4 ans (1 an d'études, 2 ans de travaux, 1 année de garantie). B- Délai d'exécution des prestations Tranche | Mission Diagnostic | Délais de…”
The core scope of work for this tender is divided into a firm tranche (Tranche Ferme) and an optional tranche (Tranche Optionnelle).
The Firm Tranche includes the following missions:
- Diagnostic (DIA): This phase involves identifying all problems, analyzing the current functioning of the system, defining and dimensioning the main characteristics of future work programs, and proposing several technical and financial scenarios. It also requires establishing a report with precise descriptions of hydraulic structures, their operating mode, identification of current weaknesses, and plans of the structures.
- Avant-Projet (AVP): This phase entails meeting with the contracting authority and operator, reviewing available documents (studies, plans, hydraulic models, functional analyses), verifying pumping group characteristics, providing a precise description of hydraulic works, pumping, and remote management systems, and conducting a critical analysis to define potential improvements and necessary future work.
- Projet (PRO): This involves defining the program of tests to verify proper dimensioning and execution of works, considering feedback from the technical controller and SPS coordinator, establishing a provisional cost for the works, and preparing a project document that includes a technical note, a test program, characteristics of automation and supervision, detailed plans, and a breakdown of the provisional cost.
- Assistance pour la passation des contrats de travaux (ACT-DCE): This mission focuses on preparing the tender documents (DCE) for work contracts, which includes technical and financial documents (CCTP, BPU/DQE or DPGF). It also covers verification of applications and offers, assistance in negotiation, drafting the definitive tender analysis report (RAO), and aiding in the finalization of the contract.
- VISA: This is a specific mission element.
- Direction de l'exécution des contrats de travaux (DET): This involves managing the execution of the work contracts.
- Ordonnancement, pilotage et coordination (OPC): This concerns the scheduling, steering, and coordination of the project.
- Assistance aux opérations de réception (AOR): This entails providing assistance during the acceptance operations for each of the structures.
The Optional Tranche includes missions for complementary studies or services:
- TO n°1 - MC 1: Scan 3D
- TO n°2 - MC 2: Diagnostic structure (Structural diagnosis)
- TO n°3 - MC 3: Diagnostic amiante et plomb (Asbestos and lead diagnosis)
- TO n°4 - MC 4: Etudes géotechniques (Geotechnical studies)
- TO n°5 - MC 5: Diagnostic de performance énergétique (Energy performance diagnosis)
- TO n°6 - MC 6: Diagnostic acoustique (Acoustic diagnosis)
- TO n°7 - MC 7: Inspection caméra (Camera inspection)
- TO n°8 - MC 8: Contrôleur Technique (Technical Controller)
The indicative duration for the overall project is 4 years, comprising 1 year for studies, 2 years for works, and 1 year for warranty. The estimated financial envelope for the works, excluding waterproofing of the SBV and Gallets pumping, is 1,700,000 € HT.
Sources
- 12_CCP_SBV_MOE-pompages.pdf — “complexité et leur intégration dans une opération globale. Proposer plusieurs scénarios possibles le cas échéant et établir une analyse comparative technique et financière permettant à la Collectivité de faire un choix p…”
- 23-1-Annexes_AE.xlsx — “ANNEXE N° 1 MISSIONS ET REPARTITIONS DES HONORAIRES,,,,,,, Enveloppe prévisionnelle des travaux : 1 700 000 Euros H.T.,,,,,,, Les pourcentages de chaque élément de mission sont les suivants :,,,,,,, ,,,,,,, TRANCHE FERME…”
- 30-1_RC_SBV_MOE-pompages.pdf — “cuve basse du réservoir de Villejean (SBV) Tous les sites hors pompage Gallets et étanchéité SBV Tranche | Mission | Pour une prestation de ΤΟ1 | | Scan 3D TO2 T03 | Missions d'assistance pour la sélection et suivi de pr…”
Login to view all answers and insights
Unlock tender brief for freeTENDER DOCUMENTS
DIRECTORY • 6 FILES
- 1_Programme_pompages_SBV-SBG.pdf25.7 MBPDF
- 3-1-Annexes_AE.xlsx21 KBXLSX
- 0-2_Confidentialite-declaration.docx53 KBDOCX
Login to view and download all tender documents
Unlock documents for freeASK AI ABOUT THIS TENDER
Can a foreign company apply?
Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.