Modernisation de l’infrastructure réseau de l’Administration Communale de Hesperange
Notice number: 00675379-2026
KEY INFORMATION
- Submission deadline
- • Oct 28, 2026
- Location
- 🇱🇺 Luxembourg
- Contracting authority
- Administration Communale de Hesperange
- Accepted Languages
- French, German
- Tender type
- Goods
- Contract Value
- Published date
- Oct 1, 2026
TENDER DESCRIPTION
This tender seeks a comprehensive modernization of the Hesperange Communal Administration's network infrastructure across three main sites, encompassing the supply, installation, configuration, and commissioning of new network equipment including Access, Core/Datacenter Switches, and a NAC Solution, all compatible with existing HPE infrastructure or equivalent. The project requires the implementation of a redundant inter-site architecture, adhering to technical specifications such as 802.1X port-based authentication, MACsec AES 256-bit, TACACS+ integration, and ISO/IEC 27001 certification. Service deliverables include an audit, target architecture design, deployment, integration, testing, and training, with a maximum execution duration of 16 weeks from the launch meeting, followed by a 5-year guarantee and maintenance period including 24/7 supervision and emergency stock. Bidders must demonstrate an average annual turnover of at least €60,000 over the last three financial years and hold professional indemnity insurance with a minimum guarantee of €1,000,000.
TENDER BRIEF
The contract timeline is structured as follows:
- Execution Phase Start: The launch meeting, which occurs at J+110 minimum, following the expiration of the standstill period and the placement of the order.
- Total Execution Duration: A maximum of 16 weeks, calculated from the launch meeting.
The key milestones and phases during the execution are:
- Audit and diagnosis: Weeks 1 to 2, starting from the launch meeting.
- Target architecture design: Weeks 3 to 5, contingent on the validation of the audit report.
- Equipment procurement: Weeks 6 to 13, following the validation of the design document, with staggered deliveries per site. This phase runs in parallel with deployment and does not extend the total duration.
- Deployment and integration: Weeks 6 to 13, with site preparation and cabling commencing from Week 6, and site-by-site migration as equipment is delivered.
- Tests and acceptance: Weeks 14 to 15, upon the completion of deployment across all three sites.
- Documentation and training: Week 16, after provisional acceptance.
The critical path for the execution phase is 3.1 → 3.2 → 3.4 → 3.5 → 3.6, totaling 16 weeks.
- Provisional Acceptance (Recette provisoire): This occurs after the completion of tests and validation, marking the end of the 16-week execution phase.
- Guarantee and Maintenance Period: This period lasts for 5 years, commencing from the date of provisional acceptance.
- Final Acceptance (Recette définitive): This takes place 12 months after the provisional acceptance, signaling the end of the legal warranty period.
Sources
- 1CDC_Hesperange.pdf — “la Loi). La procédure se déroule en deux phases distinctes : Une phase de sélection des candidatures, Une phase de remise des offres, réservées aux candidats sélectionnés. Le marché relève du Livre II de la Loi, sa valeu…”
The core scope of work for this tender, aimed at the "Modernisation réseau 2026" for the Administration Communale de Hesperange, encompasses three main areas: equipment supply, service deliverables, and maintenance.
The equipment supply includes Access Switches (REQ-1-XX), Core/Datacenter Switches (REQ-2-XX), a NAC Solution (physical appliance + licenses) (REQ-3-XX), optical modules, transceivers, connection cabling, and software licenses for management, supervision, and security. It also requires a network management and supervision platform with a single management point, advanced diagnostics, and NAC integration for Access switches. All supplied material must be new, of the latest generation, and come with a minimum 5-year manufacturer warranty. Compatibility with existing HPE infrastructure (2500, 5400, 6000 series) or equivalent equipment is mandatory, along with verifiable origin, CE conformity, and safety certifications.
The service deliverables involve:
- An audit and diagnostic of the existing infrastructure (Phase 3.1 - 2 weeks), which includes an exhaustive inventory of network equipment, detailed mapping of the current network topology, analysis of existing configurations (routing, security, QoS, VLANs, ACLs), and network flux analysis to identify congestion points. Deliverables for this phase are a technical audit report, network diagrams, and equipment inventory.
- Conception of the target architecture (Phase 3.2 - 3 weeks), focusing on the elaboration of a detailed technical solution, design of a redundant ring architecture (physical and logical), precise equipment sizing, optimized IP addressing plan and VLAN segmentation, and a security architecture (802.1X, NAC, MACsec). Deliverables include a detailed design document and architecture diagrams.
- Deployment and integration on three sites (Phase 3.4 - 8 weeks).
- Tests, acceptance, and production launch (Phase 3.5 - 2 weeks).
- Provision of technical documentation and training for the ACH teams (Phase 3.6).
Overall, these services cover the supply, installation, configuration, commissioning of new network equipment, implementation of a redundant inter-site architecture, migration services, maintenance, supervision, and operational support. The maximum contractual deadline for these phases is 16 weeks from the launch meeting.
Maintenance services are provided as an annual fee for one year and include:
- Manufacturer's hardware warranty for a minimum of 5 years.
- Preventive and corrective maintenance in accordance with SLA §9 CDC.
- An emergency stock, specifically 2 Access switches, 2 Core switches, and 1 NAC appliance, as per §9.2bis CDC.
- Firmware updates and security patches (REQ-0-01), with application within 14 days for CVSS scores ≥ 7.0 (CDC §9.4).
- 24/7 supervision and MCO, including remote surveillance, proactive real-time monitoring, intervention triggering upon alerts, and incident reports after each intervention (CDC §9.6).
- Technological watch and quarterly reports, involving analysis of technological evolutions, recommendations for optimization, and a written report delivered to ACH every three months (CDC §9.5 - 20 reports over 5 years).
Sources
- 1Annexe_C_ACH.pdf — “REQ-1-XX | Forfait | 1 | A.2 | Switches Core / Datacenter conformes REQ-2-XX | Forfait | 1 | A.3 | Solution NAC (appliance physique + licences) - conformes REQ-3-XX | Forfait | 1 | A.4 | Modules optiques, transceivers, c…”
- 2CDC_Hesperange.pdf — “planning d'exécution (diagramme de Gantt) détaillant le classement proposé, conformément au CDC §6.2.2. 3.1 Audit et diagnostic de l'existant (2 semaines) Analyse approfondie de l'infrastructure actuelle : - Inventaire e…”
- 3HcWbogyq.pdf — “comprenant notamment la fourniture, l'installation, la configuration et la mise en service de nouveaux équipements réseau, la mise en ?uvre d?une architecture inter-sites redondante, ainsi que les prestations de migratio…”
Login to view all answers and insights
Unlock tender brief for freeTENDER DOCUMENTS
DIRECTORY • 8 FILES
- Annexe_B_ACH.pdf151 KBPDF
- HcWbogyq.xml123 KBXML
- Annexe_E_Grille_Evaluation_ACH.pdf215 KBPDF
and 1 other document
Login to view and download all tender documents
Unlock documents for freeASK AI ABOUT THIS TENDER
Can a foreign company apply?
Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.
Login to ask more questions.