Published

    Saulgauer Wärme GmbH & Co. KG - Planung Gebäude und Tragwerk Heizwerk (Los 3)

    Notice number: 00568179-2026

    🇩🇪 GermanySaulgauer Wärme GmbH & Co. KGServices

    KEY INFORMATION

    Submission deadline
    Sep 15, 2026
    Location
    🇩🇪 Germany
    Contracting authority
    Saulgauer Wärme GmbH & Co. KG
    Accepted Languages
    German
    Tender type
    Services
    Contract Value
    Published date
    Aug 17, 2026

    TENDER DESCRIPTION

    This tender seeks planning services for the "Objektplanung Gebäude und Tragwerk Heizwerk (Lot 3)" as part of the "Wärmenetzinfrastruktur – Bad Saulgau" initiative, specifically covering HOAI service phases 5 to 9 for building and structural engineering, with a focus on detailed design, procurement preparation and assistance, construction supervision, and documentation. The project requires extensive coordination with other contractors and trades throughout the project lifecycle. Key technical requirements include the implementation of a process control system, dynamic setpoint control, intelligent heat generation and load management, integration of online trends like weather forecasts, and the capability for remote access and monitoring of transfer stations. The contract is projected to commence on November 4, 2024, and conclude by May 7, 2029, encompassing a total duration of approximately four years and six months, with several key milestones for operational phases. Bidders must provide declarations affirming financial stability, including freedom from insolvency or liquidation, cessation of business operations, and a self-declaration of average annual total turnover for the…

    TENDER BRIEF

    The contract timeline includes the following:

    • Contract Start Date: November 4, 2024 (for "Fördermittel Modul 2 BEW").
    • Contract End Date: May 7, 2029 ("Projektende").
    • Total Duration: Not explicitly stated as one total duration for the entire contract, but can be calculated from the start and end dates (approx. 4 years and 6 months). Various phases have their own durations, e.g., "Fördermittel Modul 2 BEW" is 1189 days and "LPH 8 - Ausführung" is 846 days.

    Key Milestones and Phases:

    • Establishment of operating company: November 7, 2024 – December 4, 2024.
    • Tendering and awarding of planning services LPH 5-8 or 9: November 8, 2024 – May 8, 2025.
    • Approval of early measures start: June 16, 2025.
    • Execution planning, tendering, and awarding of construction services: May 16, 2025 – October 9, 2025.
    • Kick-off heat center and construction section 1: October 21, 2025.
    • Receipt of grant notification: December 17, 2025.
    • First heat delivery: September 1, 2026.
    • Contract signing with planner: October 9, 2026.
    • Awarding of plant construction: December 17, 2026.
    • Building Section 2 - Start of operational phase: August 6, 2027.
    • Building Section 3 - Start of operational phase: April 27, 2028.
    • Building Section 4 - Start of operational phase: December 1, 2028.
    • End of grant period Module 2: June 15, 2029.

    Sources

    • 1Anhang_1_2025_02-SWBS-Planungsbericht+Update+Anhang.pdf — “Vergabe Leistungen zur Bauausführung 0 Tage 09.10.25 09.10.25 11 1.1.9 KickOff Heizzentrale und Bauabschnitt 1 0 Tage 21.10.25 21.10.25 12 1.1.10 Erste Wärmelieferung 0 Tage 01.09.26 01.09.26 13 1.1.11 Bauabschnitt 2 - B…
    • 2Anhang_7_20260417_Zeitplan_Akt. Endabzug.pdf — “Meilensteine BEW Fördermodul 2 / LPH 5-8 1607 Tage? Mon 16.06.25 Fre 17.10.31 9% 19 2.1.1 Bewilligung vorzeitiger Maßnahmenbeginn 0 Tage Mon 16.06.25 Mon 16.06.25 100% 20 2.1.2 Eingang Zuwendungsbescheid 1 Tag? Mit 17.12…

    The core scope of work for this tender involves planning services for the "Wärmenetzinfrastruktur – Bad Saulgau," specifically focusing on the "Objektplanung Gebäude und Tragwerk Heizwerk (Los 3)" (building planning and structural engineering for the heating plant, Lot 3). This project is part of a larger initiative to expand the existing district heating network in Bad Saulgau.

    The Statement of Work (SOW) includes "Grundleistungen" (basic services) and "Besondere Leistungen" (special services) according to HOAI Anlage 10 (for building planning) and Anlage 14 (for structural engineering).

    The core deliverables and activities span several Leistungsphasen (service phases):

    • Leistungsphase 5 (Ausführungsplanung - Detailed Design): This includes investigating the construction of the heating plant in two stages: "Grundausbau" (basic construction) and "Erweiterungspotential" (expansion potential). This also involves calculating additional costs for a two-stage expansion and requires close coordination with "Los 1".
    • Leistungsphase 6 (Vorbereitung der Vergabe - Preparation of Procurement): This phase entails preparing tender documents, specifically "Leistungsbeschreibungen mit Leistungsverzeichnissen" (performance descriptions with bills of quantities), determining and compiling quantities, coordinating interfaces with other specialized planners, and estimating costs based on priced bills of quantities. Cost control and documentation using a client-provided instrument are also required.
    • Leistungsphase 7 (Mitwirkung bei der Vergabe - Assistance in Procurement): This includes coordinating tenders from specialist planners, assisting in obtaining, reviewing, and evaluating offers (technical and economic aspects), participating in and evaluating clarification meetings with bidders, assisting in creating award proposals, and compiling contract documents. Documentation of the procurement process is also part of this phase.
    • Leistungsphase 8 (Objektüberwachung - Bauüberwachung - Construction Supervision): This involves supervising the execution of the object to ensure compliance with approvals, contracts, plans, and regulations. It also includes coordinating involved parties, establishing and monitoring a schedule, documenting the construction process (e.g., through a construction diary), checking invoices and measurements from contractors, and continuous cost control from the first award.
    • Leistungsphase 9 (Dokumentation): This is listed as a basic service for "Objektplanung Gebäude".

    Throughout these phases, the contractor must participate in various meetings, including "Planungs-Jour-Fixe" (planning meetings) and consultation meetings with the client and relevant committees for decision-making.

    Sources

    • 1260814_Leistungsbeschreibung.pdf — “Leistungsbeschreibung - Planungsleistungen Wärmenetzinfrastruktur – Bad Saulgau Objektplanung Gebäude und Tragwerk Heizwerk (Los 3) Seite 1 Leistungsbeschreibung Saulgauer Wärme GmbH & Co. KG Vergabe von Planungsleistung…
    • 2260814_Honorarangebot.xlsx — “,,,, Leistungsbild gem. HOAI,Leistungsphase gem. HOAI,Pauschalhonorar EUR/netto,Mehrwertsteuer EUR,Summe Objektplanung Gebäude Grundleistungen,5,,,0 Objektplanung Gebäude Grundleistungen,6,,,0 Objektplanung Gebäude Grund…

    Login to view all answers and insights

    Unlock tender brief for free

    TENDER DOCUMENTS

    DIRECTORY • 22 FILES

    • Anhang_9_Bestandsanlagen.pdf
    • Anhang_6_240527 Prozessleitsystem Kostenberechnung LP 3.pdf
    • 260814_Formblatt_Verhandlungsvorschlaege.docx

    and 15 other documents

    Login to view and download all tender documents

    Unlock documents for free

    ASK AI ABOUT THIS TENDER

    You

    Can a foreign company apply?

    Riko

    Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.

    Login to ask more questions.

    Unlock AI tender chat for free

    Unlock your tender workflow

    Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.

    First monitor on Day 1All features included in trialNo credit card required

    You may also be interested in

    Similar tenders