TENDER DESCRIPTION
This tender seeks comprehensive construction phase planning services for the corridor renovation at the Frankfurt (Oder) junction, specifically for VzG-Strecke 6153/6155 from Hangelberg to Oderbrücke, focusing on traffic management, ETCS implementation, and interlocking system upgrades. The scope includes leading stakeholder meetings, developing cross-trade concepts, topographical representations, and producing detailed framework construction schedules while adhering to numerous Ril standards and without the use of BIM. The contract is scheduled to commence on January 18, 2027, and conclude on December 31, 2028, with construction phase planning extending through 2029 and 2030, incorporating specific "Sperrpausen" (shutdown periods) and Quality Gate milestones. Bidders must submit offers electronically in German, ensure no multiple or alternative offers, and provide financial guarantees including an 8% contract performance bond and a 5% warranty bond for defect claims. For contracts over €100,000, a recent sustainability assessment covering key areas like human rights and environmental management is also required.
TENDER BRIEF
The contract is scheduled to begin on January 18, 2027, and conclude on December 31, 2028. The planning for the construction phases, which are expected to involve three construction states per year, extends through 2029 and 2030.
Key milestones and phases include specific "Sperrpausen" (shutdown periods):
- January 5, 2029, to January 8, 2029: TSP VzG 6153 BFUW-BZIL; VzG 6155; VzG 6156; VzG 6159/6253 (TSP entire BFP node)
- March 30, 2029, to June 18, 2029: 12*WE Strsp VzG 6156
- April 20, 2029, to September 14, 2029: TSP VzG 6153 BFP-BZIL; VzG 6155; VzG 6156; VzG 6159/6253
- April 27, 2029, to September 14, 2029: TSP VzG 6153 BERK-BFP-BZIL additionally
- March 8, 2030, to June 28, 2030: TSP VzG 6153 BERK-BFP
Additionally, Quality Gate (QG) milestones are part of the contract timeline. QG 1 occurs at the start of service delivery, while QG 2 happens during the service execution, ideally midway through the contract duration. For contracts exceeding one year, multiple QG 2s are recommended. All QG AN dates must be established as milestones within 30 calendar days following the contract award.
Sources
- 10.1_Angebotserklärung_04.08.2026.pdf — “Hinsichtlich der Beschaffung der Unterlagen gilt AVB Arch./Ing. Abschnitt 9 entsprechend. zu Ziffer 1.5.2 Richtzeichnungen/Rahmenplanungen - keine Hinsichtlich der Beschaffung der Unterlagen gilt AVB Arch./Ing. Abschnitt…”
- 21.0_Projektbeschreibung u Vorbem_Planung_03.08.2026.pdf — “davon auszugehen, dass im gleichen Bauabschnitt ebenfalls Arbeiten an Oberbau und OLA erfolgen. Diese Maßnahmen sind ebenfalls in der Bauphasenplanung zu berücksichtigen. Anlage Nr. 1 Blatt 4/7 Projektbeschreibung und Vo…”
- 313.0_Quality Gates.pdf — “QG-Sitzung auf Basis eines vorgegebenen, von vornherein bekannten Fragenkataloges (Checkliste). Die Durchführung einer Quality Gate Sitzung setzt ein übereinstimmendes Verständnis der beteiligten Partner für das gemeinsa…”
The core scope of work for this tender primarily involves the comprehensive construction phase planning for the corridor renovation at the Frankfurt (Oder) junction. The objective is to determine essential construction phases, while considering traffic management and maintaining operational activities throughout the construction period. This includes the implementation of ETCS and the interlocking system upgrade for VzG-Strecke 6153/6155, extending from Hangelberg, through Frankfurt (Oder), to Oderbrücke.
Key deliverables and tasks include:
- Leading and documenting up to 10 meetings related to construction phase planning.
- Providing textual input for the explanatory report, which encompasses a concise, chronological account of activities during main construction phases and integrating relevant activities from other trades.
- Ongoing coordination of the construction phase planning and conception with all critical project stakeholders, such as specialist planners (LST + KTB, EEA/50Hz OLA, platforms, level crossings and track, KIB), construction operation planners, construction operation coordinators, project management, and connecting parties.
- Topographical representation of track systems, construction fields, LST/ETCS, cable civil engineering, overhead lines, track, platforms, level crossings/traffic facilities, structural civil engineering, and construction site setup areas, including access routes, with continuous updates.
- Developing, coordinating, and preparing cross-trade construction phase planning and concepts in accordance with the client's regulations and work instructions.
- Creating a graphical representation of the construction phase planning, including the depiction of operational management and significant availability restrictions with textual explanations.
- Consideration of multi-year and annual construction operation planning.
- Producing a framework construction schedule (path-time diagram) that illustrates the entire construction duration, lists relevant activities with and without availability restrictions, and logically links activities as predecessor-successor relationships.
- Determining the time required for services from affected trades and assigning them to existing registered blocking periods.
- Comparing existing blocking period registrations with the identified needs across all involved trades and construction projects.
- Forming practical construction sections within registered blocking periods, ensuring that each section is assigned to only one executing party.
- Contributing to the construction logistics concept.
- All services must be comprehensive enough to ensure the success of the work contract, including any implicit services necessary for achieving the desired outcome, even if not explicitly detailed in Annex 1.
- Deliverables such as drawings, descriptions, calculations, and other elaborations must be provided in editable, open, and native digital formats (e.g., *.docx, *.xlsx, *.pptx, *.dwg, *.dxf, *.shp, *.kmz, *.X83) and in *.pdf format, on suitable data carriers.
Explicitly excluded from the scope is the technical registration of blocking periods (Sperrpausenanmeldung).
Sources
- 11.0_Projektbeschreibung u Vorbem_Planung_03.08.2026.pdf — “7 2.4 Einsatz von EDV-Systemen .................................................................................................................... 7 2.5 Definition „Mitwirken“ (für Planungsleistungen/Baugrund/Umwelt ...…”
- 21.1_Sonstige_Ingenieurleistungen_(EP).pdf — “Strecke 6153; Erkner bis Frankfurt (Oder); Bauphasenplanung: LST, Oberbau, OLA, TK, 50Hz, Hochbau Vergabenummer: 26FEI87112 Anlage 1.1 Leistungsbild Sonstige Ingenieurleistungen (EP) RIL: 208.1212Z00 - Vergabenummer: 26F…”
- 32.1_Ermittlung_der_Vergütung.pdf — “(Darstellung der gesamten Bauzeit) AN 1 Pauschale 1.7 Ermittlung des Zeitbedarfs für die Leistungen der betroffenen Gewerke und Zuordnung zu bereits angemeldeten Sperrpausen (Spp) AN 1 Pauschale 1.8 Abgleich bestehender…”
- 40.1_Angebotserklärung_04.08.2026.pdf — “bzw. deren Fachabteilungen - Fachplanern zu koordinieren sowie quantitativ und qualitativ so umfassend zu erbringen, dass der werkvertragliche Erfolg gewährleistet ist. Hierzu gehören auch alle Leistungen, die nicht ausd…”
Login to view all answers and insights
Unlock tender brief for freeTENDER DOCUMENTS
DIRECTORY • 24 FILES
- 26_Nachunternehmer-Verpflichtungserklärung.docm42 KBDOCM
- 28_Bürgschaft Vertrag.docx38 KBDOCX
- 09.0_Zu beachtende Unterlagen_03.08.2026.pdf172 KBPDF
and 17 other documents
Login to view and download all tender documents
Unlock documents for freeASK AI ABOUT THIS TENDER
Can a foreign company apply?
Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.
Login to ask more questions.
Unlock AI tender chat for freeUnlock your tender workflow
Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.