Published

    Travaux de remplacement des dispositifs d'éclairage existants par technologie led des locaux de l'institut de physique du globe de paris

    Notice number: 26-91121

    🇫🇷 FranceInstitut de Physique du Globe de Paris (IPGP)Works

    KEY INFORMATION

    Submission deadline
    • Oct 30, 2026
    Location
    🇫🇷 France
    Contracting authority
    Institut de Physique du Globe de Paris (IPGP)
    Accepted Languages
    French
    Tender type
    Works
    Contract Value
    Published date
    Sep 21, 2026

    TENDER DESCRIPTION

    This tender invites proposals for the comprehensive replacement of existing lighting devices with high-efficiency LED technology across the premises of the Institute of Earth Physics of Paris (IPGP), targeting common areas, laboratories, workshops, meeting rooms, convivial spaces, and potentially offices and sanitary facilities. The scope includes a preliminary lighting study, complete removal and WEEE-compliant disposal of current luminaires, supply and installation of new LED systems compatible with existing infrastructure and the current GTC, alongside testing, adjustments, and commissioning, culminating in a complete "Dossier des Ouvrages Exécutés." All installations must strictly comply with relevant technical standards such as AFNOR standards (e.g., NF C 15-100, NF EN 12 464-1, NF EN 15 193), Règlement ERP article EC6, and ADEME efficiency guides, ensuring integration with the existing GTC system. The contractor will manage waste according to DEEE regulations and Responsabilité Élargie des Producteurs (REP) obligations, with all supplies guaranteed for a minimum of five years. The firm tranche has a maximum execution period of seven weeks, and bidders are required to…

    TENDER BRIEF

    The contract timeline includes the following elements:

    • Contract Start Date: Services commence from the date stipulated in the technical brief.
    • Contract End Date: The contract concludes upon the date of reception of the services.
    • Total Duration: The maximum overall period for the firm tranche is set at 7 weeks.
    • Key Milestones/Phases:
    • A contract start review meeting is held within one month following the notification of the contract.
    • The tenderer is required to include a detailed execution schedule in their technical brief, which must outline provisional start and completion dates for the works, phasing and provisional intervention dates by zones, and the organization of market follow-up meetings.
    • The warranty period for the supplies cannot be less than 5 years.

    Sources

    • 1n2026MAPA00234X_CCAP _ Relamping LED.pdf — “outre, dans le cas où l'entreprise Titulaire du marché introduirait dans les documents du marché des clauses restrictives, même imposées par elle habituellement à sa clientèle, soit par l'utilisation d'imprimés particuli…”
    • 2n2026MAPA00234X_CCTP _ Relamping LED.pdf — “d'ouvrage pourra soit faire exécuter les travaux nécessaires aux frais du Titulaire, soit refuser la réception. 9.4. Levées de réserves Lorsqu'une réception avec réserves est prononcée, Le Titulaire devra réaliser les co…”

    The core scope of work for this tender involves the replacement of existing lighting devices with LED technology within the premises of the Institute of Earth Physics of Paris (IPGP). The objective is to define all necessary electrical installation works and any complementary interventions to achieve these goals.

    The Statement of Work (SOW) summarizes the following key deliverables and prestations:

    1. Preliminary Lighting Study:

    • Identification of the number, typology, and positioning of luminaires.
    • Definition of expected luminous performance.
    • Estimation of the Return-On-Investment (ROI), including anticipated financial savings from reduced electricity consumption, the ROI period, and avoided energy consumption, along with any other pertinent economic or environmental performance indicators.
    • Provision of luminaires implementation plans and calculation notes or justification elements for luminous performance.

    2. Removal of Existing Equipment:

    • Complete removal of current luminaires, which includes electrical disconnection, mechanical dismantling, removal of fixings, and cleaning/restoration of the support.
    • Evacuation of the deposed luminaires to an approved WEEE (Waste Electrical and Electronic Equipment) recycling channel, accompanied by a tracking slip.
    • Removal of existing push buttons and identification of current circuits before any intervention.

    3. Supply and Installation of New LED Luminaires:

    • Provision of all necessary high-efficiency LED luminaires, accessories, and consumables, adhering to specified performance, IPGP requirements (dimensions, color temperatures, UGR, CRI), and existing installation constraints.
    • Verification of the compatibility of new equipment with existing installations.
    • Adaptation or replacement of control devices (e.g., switches) and, if required, re-cabling and conduits.

    4. Testing, Adjustments, and Commissioning:

    • Execution of tests, adjustments, and the final commissioning of all installed lighting devices.

    5. Waste Management:

    • Evacuation of all waste materials through regulated channels, particularly for WEEE.

    6. Deliverables Post-Execution:

    • Provision of a complete "Dossier des Ouvrages Exécutés" (DOE - As-Built Dossier).
    • The DOE must include a precise implementation plan (in CAD format) of the light sources and their connections to divisional panels, a maintenance plan, and the complete lighting study.

    The market is structured into tranches:

    • Firm Tranche: Relamping of common areas, laboratories, workshops, meeting rooms, and convivial spaces.
    • Optional Tranche 1: Relamping of offices.
    • Optional Tranche 2: Relamping of sanitary facilities.

    Sources

    • 1n2026MAPA00234X_DPGF _ Relamping LED. ANNEXE 1.xlsx — “,, ,, ,, ,, ,, ,, ,, ,, ,, ,INSTITUT DE PHYSIQUE DU GLOBE DE PARIS (IPGP), ,, ,,Annexe financière à l'Acte d'Engagement ,, ,"OBJET MARCHÉ PORTANT SUR DES TRAVAUX DE REMPLACEMENT DES DISPOSITIFS D’ÉCLAIRAGE EXISTANTS PAR…”
    • 2n2026MAPA00234X_CCTP _ Relamping LED.pdf — “| 900 (pour 300 bureaux) 2.3. Définition des prestations Les prestations comprennent notamment : Dépose des anciens luminaires (mise au rebut dans le respect des filières DEEE). Fourniture et pose de nouveau luminaires L…”

    Login to view all answers and insights

    Unlock tender brief for free

    TENDER DOCUMENTS

    DIRECTORY • 7 FILES

    • n2026MAPA00234X_Visite de Site _ Relamping LED. ANNEXE 2.pdf
    • n2026MAPA00234X_CCAP _ Relamping LED.pdf
    • n2026MAPA00234X_RC _ Relamping LED.pdf

    Login to view and download all tender documents

    Unlock documents for free

    ASK AI ABOUT THIS TENDER

    You

    Can a foreign company apply?

    Riko

    Yes, foreign companies can apply as long as they meet all the requirements set out in the procurement documents.

    Login to ask more questions.

    Unlock AI tender chat for free

    Unlock your tender workflow

    Run your first search, evaluate the results, save a daily monitor and start building a pipeline of tenders worth pursuing.

    First monitor on Day 1All features included in trialNo credit card required

    You may also be interested in

    Similar tenders